logo
log in   
 
Funds raised US$543,950,100
Nets funded 248,441,097
People protected 447,193,975

Sud Ubangi Province, 2022, Congo (Dem. Rep.)  

Summary

Nets: 1,994,950 LLINs
When: Sep-Nov 23
Distributed by:  NMCP/Various


2.0 million nets will be distributed in all 16 Health Zones to achieve universal coverage (all sleeping spaces covered) across a population of some 3.3 million people.
Map

Details

 

Distribution

The distribution of nets typically takes place over a week to several months. The area District Health Service and staff typically take the lead in carrying out the on-the-ground distribution with the support and partnership of other organisations, often local or international NGOs, and with the national oversight of the National Malaria Control Program (NMCP), part of the Ministry of Health (MoH), and other funding and otherwise-contributing partners that form a distribution Task Force. Documentation is sought that shows nets were distributed as intended to beneficiaries. A distribution is typically divided into a series of locations.

Summary

  • Distribution took place between: TBA (to be advised)
  • Number of nets distributed: TBA
 

Locations

A distribution sometimes takes place in a number of locations. Each location may have its own pictures and video.

Survey status

Surveys take place 6, 18, 30 and 42 months post-distribution. A survey of 50 households provides sample information on what proportion of nets continue to be used, if they are used correctly and the state of the nets.

  • Expected
  • Not expected
  • Very good/good
  • Acceptable
  • Not OK
  • Partner Refused
# LLINs LocationWhenStatus  
102,800   Bangabola ZdS Sep-Nov 23 Status Photos expected Videos expected
113,600   Bogose Nubea ZdS Sep-Nov 23 Status Photos expected Videos expected
148,850   Bokonzi ZdS Sep-Nov 23 Status Photos expected Videos expected
86,850   Bominenge ZdS Sep-Nov 23 Status Photos expected Videos expected
125,700   Boto ZdS Sep-Nov 23 Status Photos expected Videos expected
102,800   Budjala ZdS Sep-Nov 23 Status Photos expected Videos expected
97,900   Bulu ZdS Sep-Nov 23 Status Photos expected Videos expected
158,100   Bwamanda ZdS Sep-Nov 23 Status Photos expected Videos expected
285,100   Gemena ZdS Sep-Nov 23 Status Photos expected Videos expected

Survey status

Surveys take place 6, 18, 30 and 42 months post-distribution. A survey of 50 households provides sample information on what proportion of nets continue to be used, if they are used correctly and the state of the nets.

  • Expected
  • Not expected
  • Very good/good
  • Acceptable
  • Not OK
  • Partner Refused
# LLINs LocationWhenStatus  
149,650   Kungu ZdS Sep-Nov 23 Status Photos expected Videos expected
130,450   Libenge ZdS Sep-Nov 23 Status Photos expected Videos expected
88,450   Mawuya ZdS Sep-Nov 23 Status Photos expected Videos expected
55,050   Mbaya ZdS Sep-Nov 23 Status Photos expected Videos expected
102,000   Ndage ZdS Sep-Nov 23 Status Photos expected Videos expected
184,400   Tandala ZdS Sep-Nov 23 Status Photos expected Videos expected
63,250   Zongo ZdS Sep-Nov 23 Status Photos expected Videos expected

Distribution status

The bednet distribution programmes go through a number of different states from being manufactured to being installed over a head/bed:
  • Being manufactured
  • Ready at factory
  • En-route to country
  • Arrived in country
  • En-route to zone
  • Being distributed
  • Distribution complete

Libenge ZdS, Congo (Dem. Rep.)

 

Status Distribution complete Distribution complete