Funds raised US$760,713,553
Nets funded 345,402,739
People protected 621,724,930

6 regions, Guinea  

Summary

Nets: 4,752,150 LLINs
When: Apr-Jul 25
Distributed by:  NMCP/Various


4.75 million nets will be distributed in 21 prefectures across six regions to achieve universal coverage (all sleeping spaces covered) across a population of 8.6 million people.
Map

Details

 

Distribution

The distribution of nets typically takes place over a week to several months. The area District Health Service and staff typically take the lead in carrying out the on-the-ground distribution with the support and partnership of other organisations, often local or international NGOs, and with the national oversight of the National Malaria Control Program (NMCP), part of the Ministry of Health (MoH), and other funding and otherwise-contributing partners that form a distribution Task Force. Documentation is sought that shows nets were distributed as intended to beneficiaries. A distribution is typically divided into a series of locations.

Summary

  • Distribution took place between W1 April 2025, W2 May 2025
  • Number of nets distributed: 2,721,481 as of June 2025
 

Locations

A distribution sometimes takes place in a number of locations. Each location may have its own pictures and video.

Survey status

Surveys take place 6, 18, 30 and 42 months post-distribution. A survey of 50 households provides sample information on what proportion of nets continue to be used, if they are used correctly and the state of the nets.

  • Expected
  • Not expected
  • Very good/good
  • Acceptable
  • Not OK
  • Partner Refused

Survey status

Surveys take place 6, 18, 30 and 42 months post-distribution. A survey of 50 households provides sample information on what proportion of nets continue to be used, if they are used correctly and the state of the nets.

  • Expected
  • Not expected
  • Very good/good
  • Acceptable
  • Not OK
  • Partner Refused
# LLINs LocationWhenStatus  
416,800   Boké région, Boké préfecture Jun-Jul 25 Status Photos expected Videos expected
84,350   Boké région, Fria préfecture Jun-Jul 25 Status Photos expected Videos expected
270,600   Labé région, Labé préfecture Jun-Jul 25 Status Photos expected Videos expected
103,500   Labé région, Lélouma préfecture Jun-Jul 25 Status Photos expected Videos expected
176,850   Boké région, Gaoual préfecture Jul 25 Status Photos expected Videos expected
111,500   Boké région, Koundara préfecture Jul 25 Status Photos expected Videos expected
319,950   Kindia région, Coyah préfecture Jul 25 Status Photos expected Videos expected
367,050   Kindia région, Dubréka préfecture Jul 25 Status Photos expected Videos expected
66,650   Labé région, Koubia préfecture Jul 25 Status Photos expected Videos expected
185,500   Labé région, Mali préfecture Jul 25 Status Photos expected Videos expected
89,500   Labé région, Tougué préfecture Jul 25 Status Photos expected Videos expected

Distribution status

The bednet distribution programmes go through a number of different states from being manufactured to being installed over a head/bed:
  • Being manufactured
  • Ready at factory
  • En-route to country
  • Arrived in country
  • En-route to zone
  • Being distributed
  • Distribution complete