Funds raised US$760,713,553
Nets funded 345,402,739
People protected 621,724,930

14/23 provinces, 2026, Chad  

Summary

Nets: 8,272,050 LLINs
When: Jan-May 26
Distributed by:  NMCP/Various


8.3 million nets will be distributed in 14 of 23 provinces to achieve universal coverage (all sleeping spaces covered) across a population of 15 million people.
Map

Details

 

Donations funding nets    

We allocate donations individually to specific distributions. This is consistent with being accountable and transparent with the funds we receive. It also allows donors to engage with a net distribution by being able to follow the progress of the nets they have funded. A distribution is typically divided into a series of locations.

Summary

  • 4,422 donations from 2,945 donors in 57 countries
  • Smallest donation: AUD1.00, largest donation: CAD250,000
  • (*Figures are 'to date' as funds are still being allocated)

Locations

Click on a location to view the donations that funded it.

Survey status

Surveys take place 6, 18, 30 and 42 months post-distribution. A survey of 50 households provides sample information on what proportion of nets continue to be used, if they are used correctly and the state of the nets.

  • Expected
  • Not expected
  • Very good/good
  • Acceptable
  • Not OK
  • Partner Refused
# LLINs LocationWhenStatus
721,350   Mandoul Province Jan 26 Status
616,900   Moyen Chari Province Jan 26 Status
314,000   Salamat Province Jan 26 Status
719,700   Logone Occidental Province Feb 26 Status
827,800   Logone Oriental Province Feb 26 Status
694,450   Tandjile Province Feb 26 Status
589,000   Chari Baguirmi Province Mar 26 Status
799,300   Mayo Kebbi Est Province Mar 26 Status

Survey status

Surveys take place 6, 18, 30 and 42 months post-distribution. A survey of 50 households provides sample information on what proportion of nets continue to be used, if they are used correctly and the state of the nets.

  • Expected
  • Not expected
  • Very good/good
  • Acceptable
  • Not OK
  • Partner Refused
# LLINs LocationWhenStatus
588,325   Mayo Kebbi Ouest Province Mar 26 Status
411,650   N'djamena Province Mar 26 Status
480,250   Batha Province May 26 Status
489,250   Guera Province May 26 Status
573,950   Hadjer Lamis Province May 26 Status
446,125   Sila Province May 26 Status

Distribution status

The bednet distribution programmes go through a number of different states from being manufactured to being installed over a head/bed:
  • Pre-manufacture
  • Being manufactured
  • Ready at factory
  • En-route to country
  • Arrived in country
  • En-route to zone
  • Being distributed
  • Distribution complete