logo
login
 
Funds raised US$760,713,553
Nets funded 345,402,739
People protected 621,724,930

Bauchi State, 2026, Nigeria  

Summary

Nets: 4,876,700 LLINs
When: May 26
Distributed by:  NMCP/Various


4.9 million nets will be distributed in all 20 health zones to achieve universal coverage (all sleeping spaces covered) across a population of some 8.8 million people.
Map

Details

 

Donations funding nets    

We allocate donations individually to specific distributions. This is consistent with being accountable and transparent with the funds we receive. It also allows donors to engage with a net distribution by being able to follow the progress of the nets they have funded. A distribution is typically divided into a series of locations.

Summary

  • 4,685 donations from 3,389 donors in 62 countries
  • Smallest donation: US$1.00, largest donation: €81,391
  • (*Figures are 'to date' as funds are still being allocated)

Locations

Click on a location to view the donations that funded it.

Survey status

Surveys take place 6, 18, 30 and 42 months post-distribution. A survey of 50 households provides sample information on what proportion of nets continue to be used, if they are used correctly and the state of the nets.

  • Expected
  • Not expected
  • Very good/good
  • Acceptable
  • Not OK
  • Partner Refused
# LLINs LocationWhenStatus
344,050   Alkaleri LGA May 26 Status
517,450   Bauchi LGA May 26 Status
87,850   Bogoro LGA May 26 Status
157,450   Damban LGA May 26 Status
261,950   Darazo LGA May 26 Status
94,450   Dass LGA May 26 Status
298,100   Gamawa LGA May 26 Status
291,850   Ganjuwa LGA May 26 Status
163,500   Giade LGA May 26 Status
239,500   Itas/Gadau LGA May 26 Status
123,150   Jama'are LGA May 26 Status

Survey status

Surveys take place 6, 18, 30 and 42 months post-distribution. A survey of 50 households provides sample information on what proportion of nets continue to be used, if they are used correctly and the state of the nets.

  • Expected
  • Not expected
  • Very good/good
  • Acceptable
  • Not OK
  • Partner Refused
# LLINs LocationWhenStatus
307,100   Katagum LGA May 26 Status
152,650   Kirfi LGA May 26 Status
273,950   Misau LGA May 26 Status
404,550   Ningi LGA May 26 Status
245,250   Shira LGA May 26 Status
231,950   Tafawa-Balewa LGA May 26 Status
362,650   Toro LGA May 26 Status
120,500   Warji LGA May 26 Status
198,800   Zaki LGA May 26 Status

Distribution status

The bednet distribution programmes go through a number of different states from being manufactured to being installed over a head/bed:
  • Pre-manufacture
  • Being manufactured
  • Ready at factory
  • En-route to country
  • Arrived in country
  • En-route to zone
  • Being distributed
  • Distribution complete