Eastern and Central, 2026, Zambia  

Summary

Nets: 4,042,800 LLINs
When: Oct 26
Distributed by:  NMCP/Various


4.7 million nets will be distributed in four provinces to achieve universal coverage (all sleeping spaces covered) across a population of some 8.5 million people.
Map

Details

 

Donations funding nets    

We allocate donations individually to specific distributions. This is consistent with being accountable and transparent with the funds we receive. It also allows donors to engage with a net distribution by being able to follow the progress of the nets they have funded. A distribution is typically divided into a series of locations.

Summary

  • 5 donations from 1 donors in 1 countries
  • Smallest donation: US$200,000.00, largest donation: US$200,000
  • (*Figures are 'to date' as funds are still being allocated)

Locations

Click on a location to view the donations that funded it.

Survey status

Surveys take place 6, 18, 30 and 42 months post-distribution. A survey of 50 households provides sample information on what proportion of nets continue to be used, if they are used correctly and the state of the nets.

  • Expected
  • Not expected
  • Very good/good
  • Acceptable
  • Not OK
  • Partner Refused
# LLINs LocationWhenStatus
113,050   Chama, Eastern province Oct 26 Status
336,650   Chibombo, Central province Oct 26 Status
85,900   Chililabombwe, Copperbelt province Oct 26 Status
193,950   Chingola, Copperbelt province Oct 26 Status
102,100   Chisamba, Central province Oct 26 Status
70,000   Chitambo, Central province Oct 26 Status
79,300   Isoka, Muchinga province Oct 26 Status
219,950   Kabwe, Central province Oct 26 Status
101,600   Kalulushi, Copperbelt province Oct 26 Status
80,800   Kanchibiya, Muchinga province Oct 26 Status
312,050   Kapiri Mposhi, Central province Oct 26 Status
491,800   Kitwe, Copperbelt province Oct 26 Status
78,600   Luano, Central province Oct 26 Status
150,650   Luanshya, Copperbelt province Oct 26 Status

Survey status

Surveys take place 6, 18, 30 and 42 months post-distribution. A survey of 50 households provides sample information on what proportion of nets continue to be used, if they are used correctly and the state of the nets.

  • Expected
  • Not expected
  • Very good/good
  • Acceptable
  • Not OK
  • Partner Refused
# LLINs LocationWhenStatus
98,700   Lufwanyama, Copperbelt province Oct 26 Status
72,650   Mafinga, Muchinga province Oct 26 Status
98,450   Masaiti, Copperbelt province Oct 26 Status
166,400   Mkushi, Central province Oct 26 Status
132,850   Mpongwe, Copperbelt province Oct 26 Status
155,100   Mufulira, Copperbelt province Oct 26 Status
210,750   Mumbwa, Central province Oct 26 Status
416,850   Ndola, Copperbelt province Oct 26 Status
32,950   Ngabwe, Central province Oct 26 Status
99,600   Serenje, Central province Oct 26 Status
72,450   Shibuyunji, Central province Oct 26 Status
69,650   Shiwang'andu, Muchinga province Oct 26 Status

Distribution status

The bednet distribution programmes go through a number of different states from being manufactured to being installed over a head/bed:
  • Pre-manufacture
  • Being manufactured
  • Ready at factory
  • En-route to country
  • Arrived in country
  • En-route to zone
  • Being distributed