Summary

Nets: 1,739,100 LLINs
When: Dec 20-Feb 21
Distributed by:  PNLP/TBD


1.7 million nets will be distributed in all 18 of the health zones in Maniema province to achieve universal coverage of a population of 3.1 million people. This is part of a commitment made by AMF to fund 16.2 million nets for distribution in DRC in 2020.
Map

Details

 

Donations funding nets     view donations funding non-net costs

We allocate donations individually to specific distributions. This is consistent with being accountable and transparent with the funds we receive. It also allows donors to engage with a net distribution by being able to follow the progress of the nets they have funded. A distribution is typically divided into a series of locations.

Summary

  • Total funding required for nets: US$3,478,200 (est)
  • 6,319 donations from 4,091 donors in 67 countries
  • Smallest donation: £1.00, largest donation: US$200,000
  • (*Figures are 'to date' as funds are still being allocated)

Locations

Click on a location to view the donations that funded it.

Survey status

Surveys take place 6, 18, 30 and 42 months post-distribution. A survey of 50 households provides sample information on what proportion of nets continue to be used, if they are used correctly and the state of the nets.

  • Expected
  • Not expected
  • Very good/good
  • Acceptable
  • Not OK
  • Partner Refused
# LLINs LocationWhenStatus
67,400   Alunguli ZdS, Maniema Province Dec 20-Feb 21 Status
41,700   Ferekeni ZdS, Maniema Province Dec 20-Feb 21 Status
75,300   Kabambare ZdS, Maniema Province Dec 20-Feb 21 Status
115,300   Kailo ZdS, Maniema Province Dec 20-Feb 21 Status
103,000   Kalima ZdS, Maniema Province Dec 20-Feb 21 Status
101,850   Kampene ZdS, Maniema Province Dec 20-Feb 21 Status
148,000   Kasongo ZdS, Maniema Province Dec 20-Feb 21 Status
72,550   Kibombo ZdS, Maniema Province Dec 20-Feb 21 Status
191,150   Kindu ZdS, Maniema Province Dec 20-Feb 21 Status
189,800   Kunda ZdS, Maniema Province Dec 20-Feb 21 Status

Survey status

Surveys take place 6, 18, 30 and 42 months post-distribution. A survey of 50 households provides sample information on what proportion of nets continue to be used, if they are used correctly and the state of the nets.

  • Expected
  • Not expected
  • Very good/good
  • Acceptable
  • Not OK
  • Partner Refused
# LLINs LocationWhenStatus
90,250   Lubutu ZdS, Maniema Province Dec 20-Feb 21 Status
114,150   Lusangi ZdS, Maniema Province Dec 20-Feb 21 Status
52,350   Obokote ZdS, Maniema Province Dec 20-Feb 21 Status
60,200   Pangi ZdS, Maniema Province Dec 20-Feb 21 Status
72,800   Punia ZdS, Maniema Province Dec 20-Feb 21 Status
81,600   Samba ZdS, Maniema Province Dec 20-Feb 21 Status
106,550   Saramabila ZdS, Maniema Province Dec 20-Feb 21 Status
55,150   Tunda ZdS, Maniema Province Dec 20-Feb 21 Status

Distribution status

The bednet distribution programmes go through a number of different states from being manufactured to being installed over a head/bed:
  • Pre-manufacture
  • Being manufactured
  • Ready at factory
  • En-route to country
  • Arrived in country
  • En-route to zone
  • Being distributed
  • Distribution complete