Plateau State, 2023, Nigeria  

Summary

Nets: 2,998,650 LLINs
When: Apr 24
Distributed by:  NMCP/Various


3.0 million nets will be distributed in all Health Zones in 17 regions to achieve universal coverage (all sleeping spaces covered) across a population of some 5.4 million people.
Map

Details

 

Distribution

The distribution of nets typically takes place over a week to several months. The area District Health Service and staff typically take the lead in carrying out the on-the-ground distribution with the support and partnership of other organisations, often local or international NGOs, and with the national oversight of the National Malaria Control Program (NMCP), part of the Ministry of Health (MoH), and other funding and otherwise-contributing partners that form a distribution Task Force. Documentation is sought that shows nets were distributed as intended to beneficiaries. A distribution is typically divided into a series of locations.

Summary

  • Distribution will take place from 13th April 2024 - 21st April 2024
  • Number of nets distributed: TBA
 

Locations

A distribution sometimes takes place in a number of locations. Each location may have its own pictures and video.

Survey status

Surveys take place 6, 18, 30 and 42 months post-distribution. A survey of 50 households provides sample information on what proportion of nets continue to be used, if they are used correctly and the state of the nets.

  • Expected
  • Not expected
  • Very good/good
  • Acceptable
  • Not OK
  • Partner Refused
# LLINs LocationWhenStatus  
168,150   Barikin Ladi LGA, Plateau Apr 24 Status Photos expected Videos expected
177,550   Bassa LGA, Plateau Apr 24 Status Photos expected Videos expected
167,900   Bokkos LGA, Plateau Apr 24 Status Photos expected Videos expected
82,600   Jos East LGA, Plateau Apr 24 Status Photos expected Videos expected
408,800   Jos North LGA, Plateau Apr 24 Status Photos expected Videos expected
291,200   Jos South LGA, Plateau Apr 24 Status Photos expected Videos expected
156,750   Kanam LGA, Plateau Apr 24 Status Photos expected Videos expected
116,200   Kanke LGA, Plateau Apr 24 Status Photos expected Videos expected
133,100   Langtang North LGA, Plateau Apr 24 Status Photos expected Videos expected

Survey status

Surveys take place 6, 18, 30 and 42 months post-distribution. A survey of 50 households provides sample information on what proportion of nets continue to be used, if they are used correctly and the state of the nets.

  • Expected
  • Not expected
  • Very good/good
  • Acceptable
  • Not OK
  • Partner Refused
# LLINs LocationWhenStatus  
98,350   Langtang South LGA, Plateau Apr 24 Status Photos expected Videos expected
281,050   Mangu LGA, Plateau Apr 24 Status Photos expected Videos expected
90,150   Mikang LGA, Plateau Apr 24 Status Photos expected Videos expected
177,800   Pankshin LGA, Plateau Apr 24 Status Photos expected Videos expected
184,500   Quaan Pan LGA, Plateau Apr 24 Status Photos expected Videos expected
123,250   Riyom LGA, Plateau Apr 24 Status Photos expected Videos expected
191,800   Shendam LGA, Plateau Apr 24 Status Photos expected Videos expected
149,500   Wase LGA, Plateau Apr 24 Status Photos expected Videos expected

Distribution status

The bednet distribution programmes go through a number of different states from being manufactured to being installed over a head/bed:
  • Being manufactured
  • Ready at factory
  • En-route to country
  • Arrived in country
  • En-route to zone
  • Being distributed
  • Distribution complete