Funds raised US$541,355,209
Nets funded 247,136,740
People protected 444,846,132

6 Provinces, 2023, Zambia  

Summary

Nets: 6,291,900 LLINs
When: Oct 23-Jan 24
Distributed by:  NMCP/Various


6.3 million nets will be distributed in 74 districts in six provinces to achieve universal coverage (all sleeping spaces covered) across a population of 11.3 million people.
Map

Details

 

Donations funding nets    

We allocate donations individually to specific distributions. This is consistent with being accountable and transparent with the funds we receive. It also allows donors to engage with a net distribution by being able to follow the progress of the nets they have funded. A distribution is typically divided into a series of locations.

Summary

  • 14,508 donations from 5,190 donors in 11 countries
  • Smallest donation: AUD1.00, largest donation: US$250,000
  • (*Figures are 'to date' as funds are still being allocated)

Locations

Click on a location to view the donations that funded it.

Survey status

Surveys take place 6, 18, 30 and 42 months post-distribution. A survey of 50 households provides sample information on what proportion of nets continue to be used, if they are used correctly and the state of the nets.

  • Expected
  • Not expected
  • Very good/good
  • Acceptable
  • Not OK
  • Partner Refused
# LLINs LocationWhenStatus
74,750   Chadiza, Eastern province Oct 23 Status
92,100   Chama, Eastern province Oct 23 Status
79,700   Chasefu, Eastern province Oct 23 Status
30,550   Chembe, Luapula province Oct 23 Status
155,700   Chiengi, Luapula province Oct 23 Status
69,750   Chifunabuli, Luapula province Oct 23 Status
119,400   Chipangali, Eastern province Oct 23 Status
187,100   Chipata, Eastern province Oct 23 Status
34,400   Chipili, Luapula province Oct 23 Status
80,300   Kasenengwa, Eastern province Oct 23 Status
137,700   Katete, Eastern province Oct 23 Status
66,500   Kawambwa, Luapula province Oct 23 Status
112,600   Lumezi, Eastern province Oct 23 Status
104,750   Lundazi, Eastern province Oct 23 Status
22,900   Lunga, Luapula province Oct 23 Status
44,150   Lusangazi, Eastern province Oct 23 Status
71,650   Mambwe, Eastern province Oct 23 Status
234,050   Mansa, Luapula province Oct 23 Status
35,850   Milenge, Luapula province Oct 23 Status
48,000   Mwansabombwe, Luapula province Oct 23 Status
92,050   Mwense, Luapula province Oct 23 Status
142,250   Nchelenge, Luapula province Oct 23 Status
87,600   Nyimba, Eastern province Oct 23 Status
184,500   Petauke, Eastern province Oct 23 Status
126,650   Samfya, Luapula province Oct 23 Status
133,750   Sinda, Eastern province Oct 23 Status
37,300   Vubwi, Eastern province Oct 23 Status
37,050   Chavuma, North-Western province Nov 23 Status
84,500   Chilubi, Northern province Nov 23 Status
84,850   Chinsali, Muchinga province Nov 23 Status
35,600   Ikelenge, North-Western province Nov 23 Status
84,200   Isoka, Muchinga province Nov 23 Status
48,450   Kabompo, North-Western province Nov 23 Status
170,750   Kalumbila, North-Western province Nov 23 Status
72,550   Kanchibiya, Muchinga province Nov 23 Status
60,250   Kaputa, Northern province Nov 23 Status
278,500   Kasama, Northern province Nov 23 Status
83,800   Kasempa, North-Western province Nov 23 Status

Survey status

Surveys take place 6, 18, 30 and 42 months post-distribution. A survey of 50 households provides sample information on what proportion of nets continue to be used, if they are used correctly and the state of the nets.

  • Expected
  • Not expected
  • Very good/good
  • Acceptable
  • Not OK
  • Partner Refused
# LLINs LocationWhenStatus
51,050   Lavushimanda, Muchinga province Nov 23 Status
55,500   Lunte, Northern province Nov 23 Status
67,150   Lupososhi, Northern province Nov 23 Status
49,950   Luwingu, Northern province Nov 23 Status
72,350   Mafinga, Muchinga province Nov 23 Status
47,250   Manyinga, North-Western province Nov 23 Status
96,000   Mbala, Northern province Nov 23 Status
119,500   Mpika, Muchinga province Nov 23 Status
46,900   Mporokoso, Northern province Nov 23 Status
153,700   Mpulungu, Northern province Nov 23 Status
86,400   Mufumbwe, North-Western province Nov 23 Status
167,500   Mungwi, Northern province Nov 23 Status
60,600   Mushindamo, North-Western province Nov 23 Status
83,700   Mwinilunga, North-Western province Nov 23 Status
126,600   Nakonde, Muchinga province Nov 23 Status
50,150   Nsama, Northern province Nov 23 Status
110,600   Senga, Northern province Nov 23 Status
64,300   Shiwang'andu, Muchinga province Nov 23 Status
190,900   Solwezi, North-Western province Nov 23 Status
60,000   Zambezi, North-Western province Nov 23 Status
81,300   Kalabo, Western province Dec 23-Jan 24 Status
118,300   Kaoma, Western province Dec 23-Jan 24 Status
37,900   Limulunga, Western province Dec 23-Jan 24 Status
43,450   Luampa, Western province Dec 23-Jan 24 Status
59,400   Lukulu, Western province Dec 23-Jan 24 Status
28,050   Mitete, Western province Dec 23-Jan 24 Status
132,800   Mongu, Western province Dec 23-Jan 24 Status
29,300   Mulobezi, Western province Dec 23-Jan 24 Status
24,200   Mwandi, Western province Dec 23-Jan 24 Status
53,900   Nalolo, Western province Dec 23-Jan 24 Status
30,350   Nkeyema, Western province Dec 23-Jan 24 Status
78,000   Senanga, Western province Dec 23-Jan 24 Status
43,900   Sesheke, Western province Dec 23-Jan 24 Status
50,200   Shang'ombo, Western province Dec 23-Jan 24 Status
35,800   Sikongo, Western province Dec 23-Jan 24 Status
38,450   Sioma, Western province Dec 23-Jan 24 Status

Distribution status

The bednet distribution programmes go through a number of different states from being manufactured to being installed over a head/bed:
  • Pre-manufacture
  • Being manufactured
  • Ready at factory
  • En-route to country
  • Arrived in country
  • En-route to zone
  • Being distributed
  • Distribution complete