Funds raised US$627,215,190
Nets funded 286,511,672
People protected 515,721,010

Nord Kivu Province, 2024, Congo (Dem. Rep.)  

Summary

Nets: 1,225,300 LLINs
When: Mar-Apr 25
Distributed by:  PNLP/TBD


1.2 million nets will be distributed in all nine health zones to achieve universal coverage (all sleeping spaces covered) across a population of some 2.2 million people.
Map

Details

 

Donations funding nets    

We allocate donations individually to specific distributions. This is consistent with being accountable and transparent with the funds we receive. It also allows donors to engage with a net distribution by being able to follow the progress of the nets they have funded. A distribution is typically divided into a series of locations.

Summary

  • 5,545 donations from 2,396 donors in 12 countries
  • Smallest donation: US$5.00, largest donation: US$500,000
  • (*Figures are 'to date' as funds are still being allocated)

Locations

Click on a location to view the donations that funded it.

Survey status

Surveys take place 6, 18, 30 and 42 months post-distribution. A survey of 50 households provides sample information on what proportion of nets continue to be used, if they are used correctly and the state of the nets.

  • Expected
  • Not expected
  • Very good/good
  • Acceptable
  • Not OK
  • Partner Refused
# LLINs LocationWhenStatus
93,250   Biena ZdS Mar-Apr 25 Status
126,600   Binza ZdS Mar-Apr 25 Status
130,100   Itebero ZdS Mar-Apr 25 Status
256,950   Kibirizi ZdS Mar-Apr 25 Status
79,400   Kibua ZdS Mar-Apr 25 Status

Survey status

Surveys take place 6, 18, 30 and 42 months post-distribution. A survey of 50 households provides sample information on what proportion of nets continue to be used, if they are used correctly and the state of the nets.

  • Expected
  • Not expected
  • Very good/good
  • Acceptable
  • Not OK
  • Partner Refused
# LLINs LocationWhenStatus
57,400   Manguredjipa ZdS Mar-Apr 25 Status
119,250   Pinga ZdS Mar-Apr 25 Status
220,950   Rutshuru ZdS Mar-Apr 25 Status
141,400   Walikale ZdS Mar-Apr 25 Status

Distribution status

The bednet distribution programmes go through a number of different states from being manufactured to being installed over a head/bed:
  • Pre-manufacture
  • Being manufactured
  • Ready at factory
  • En-route to country
  • Arrived in country
  • En-route to zone
  • Being distributed
  • Distribution complete