Summary

Nets: 3,306,800 LLINs
When: Jun 23
Distributed by:  NMCP/Various


3.3 million nets will be distributed to achieve universal coverage (all sleeping spaces covered) across a population of some 6 million people.
Map

Details

 

Donations funding nets    

We allocate donations individually to specific distributions. This is consistent with being accountable and transparent with the funds we receive. It also allows donors to engage with a net distribution by being able to follow the progress of the nets they have funded. A distribution is typically divided into a series of locations.

Summary

  • 14,370 donations from 7,114 donors in 78 countries
  • Smallest donation: US$1.00, largest donation: US$500,000
  • (*Figures are 'to date' as funds are still being allocated)

Locations

Click on a location to view the donations that funded it.

Survey status

Surveys take place 6, 18, 30 and 42 months post-distribution. A survey of 50 households provides sample information on what proportion of nets continue to be used, if they are used correctly and the state of the nets.

  • Expected
  • Not expected
  • Very good/good
  • Acceptable
  • Not OK
  • Partner Refused
# LLINs LocationWhenStatus
233,300   Alkaleri LGA Jun 23 Status
350,850   Bauchi LGA Jun 23 Status
59,550   Bogoro LGA Jun 23 Status
106,750   Damban LGA Jun 23 Status
177,650   Darazo LGA Jun 23 Status
64,050   Dass LGA Jun 23 Status
202,100   Gamawa LGA Jun 23 Status
197,900   Ganjuwa LGA Jun 23 Status
110,900   Giade LGA Jun 23 Status
162,400   Itas/Gadau LGA Jun 23 Status
83,500   Jama'are LGA Jun 23 Status

Survey status

Surveys take place 6, 18, 30 and 42 months post-distribution. A survey of 50 households provides sample information on what proportion of nets continue to be used, if they are used correctly and the state of the nets.

  • Expected
  • Not expected
  • Very good/good
  • Acceptable
  • Not OK
  • Partner Refused
# LLINs LocationWhenStatus
208,250   Katagum LGA Jun 23 Status
103,500   Kirfi LGA Jun 23 Status
185,800   Misau LGA Jun 23 Status
274,300   Ningi LGA Jun 23 Status
166,300   Shira LGA Jun 23 Status
157,300   Tafawa-Balewa LGA Jun 23 Status
245,900   Toro LGA Jun 23 Status
81,700   Warji LGA Jun 23 Status
134,800   Zaki LGA Jun 23 Status

Distribution status

The bednet distribution programmes go through a number of different states from being manufactured to being installed over a head/bed:
  • Pre-manufacture
  • Being manufactured
  • Ready at factory
  • En-route to country
  • Arrived in country
  • En-route to zone
  • Being distributed
  • Distribution complete